No. |
Project Description |
Project Owner/ Client |
Completion Year |
1 |
Provision of Developing and Update Operational Safety Case, QRA and HAZOP, HAZID, SIL and safety studies for FPSO MV34 |
MODEC Offshore Production Systems (Singapore) Pte. Ltd |
(in progress) |
2 |
Provision of HAZOP revalidation, Quantative Risk Assessment and Safety Case Update and Integrity review service for WHP-MT1, WHP-HT1 and PQP-HT |
Bien Dong POC |
(in progress) |
3 |
Provision of Operation Safety Case Update for FSO PTSC Bien Dong |
PTSC |
(in progress) |
4 |
Provision of Operation HSE Cases and QRA for Su Tu Field Facilities (include 5 Operation Safety Case cho WHP-A; WHP-B; STT Facilities; STV CPP; TBVN FPSO) |
Cuu Long Joint Operating Company |
2017 |
5 |
Preparation of Operations HSE Case for CLJOC Su Tu Vang South West and Su Tu Vang North East Wellhead Platforms |
Cuu Long Joint Operating Company (CLJOC) |
2015 |
6 |
Provision of Update Operations Safety Case (including QRA, HAZOP, SCA, MOPO Studies) and acquisition of MoIT/ PVN approval for the prepared QRA for PTSC FPSO Ruby II |
PTSC (Production Services) |
2016 |
7 |
Provision of Safety Studies (including Noise Study, AIV Study, TR Impairment Analysis, Hazards and Effect Register, Design HSE Case, and MOPO/ SIMOPs Study) for CLJOC Su Tu Trang Full Field Development Phase 1 – Detailed Engineering |
Cuu Long JOC / PV Engineering |
2015 |
8 |
Preparation of Update Operations Safety Case for LSJOC Thang Long – Dong Do Wellhead Platform |
Lam Son Joint Operating Company (LSJOC) |
2014 |
9 |
Provision of Operations HSE Case Update STD SW and STV CPP |
Cuu Long Joint Operating Company (CLJOC) |
2009 |
10 |
English-Vietnamese translation of Chim Sao Safety Case Document, Emergency Response Plan Document |
Premier Oil |
2011 |